Breakup

26.24.1 PVC soap tray

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 PVC soap tray Material: (A) 1 no 60 each 60 60
2 50 mm screw & rowel plug Installation cost: (B) Accessories: Rowel plug and screw 2 no 9 each 9 18
3 Plumber Labour: Plumber 0.015 no 700 per day 700 10.5
4 Skilled labour Skilled labour 0.01 no 600 per day 600 6
5 Ordinary labour Ordinary labour 0.05 no 550 per day 550 27.5
Sub-Total 122
Contractor's Profit 10% 0.1 12.2
Contractor's Overhead Expenses 3.5% 0.035 4.27
Total 138.47
Add VAT with adjustment factor. 1.08108 7.5% 0.075 11.23
Grand Total 149.7
Rate per each 150
Rate per each 150