Breakup

26.24.4 Stainless steel soap tray

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Stainless steel soap tray Material: (A) 1 no 450 each 450 450
2 50 mm screw & rowel plug Installation cost: (B) Accessories: Rowel plug and screw 2 no 9 each 9 18
3 Plumber Labour: Plumber 0.015 no 700 per day 700 10.5
4 Skilled labour Skilled labour 0.01 no 600 per day 600 6
5 Ordinary labour Ordinary labour 0.05 no 550 per day 550 27.5
Sub-Total 512
Contractor's Profit 10% 0.1 51.2
Contractor's Overhead Expenses 3.5% 0.035 17.92
Total 581.12
Add VAT with adjustment factor. 1.08108 7.5% 0.075 47.12
Grand Total 628.24
Rate per each 628
Rate per each 628