Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 125 mm dia convex cast iron grating on rain water down pipe (roof top) Material cost: (A) | 1 | no | 400 | each | 400 | 400 | |
| 2 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials: Cement mortar (1:4) Cement | 0.01 | bag | 410 | per bag | 410 | 4.1 | |
| 3 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 0.05 | cft | 1900 | per % cft | 19 | 0.95 | |
| 4 | Skilled labour Labour: Skilled labour | 0.05 | no | 600 | per day | 600 | 30 | |
| 5 | Carriage | LS | 16 | |||||
| Sub-Total | 451.05 | |||||||
| Contractor's Profit | 10% | 0.1 | 45.11 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 15.79 | |||||
| Total | 511.95 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 41.51 | ||||
| Grand Total | 553.46 | |||||||
| Rate per each | 553 | |||||||
| Rate per each | 553 | |||||||