Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm floor drain with vertical outlet Material cost: (A) | 1 | no | 1050 | each | 1050 | 1050 | |
| 2 | Solvent cement Installation cost: (B) Fitting fixing materials: Solvent cement | 13.5 | ml | 0.85 | per ml | 0.85 | 11.47 | |
| 3 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement mortar (1:4) Cement | 0.02 | bag | 410 | per bag | 410 | 8.2 | |
| 4 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 0.1 | cft | 1900 | per % cft | 19 | 1.9 | |
| 5 | Plumber Labour: Plumber | 0.02 | no | 700 | per day | 700 | 14 | |
| 6 | Skilled labour Skilled labour | 0.05 | no | 600 | per day | 600 | 30 | |
| Sub-Total | 1115.57 | |||||||
| Contractor's Profit | 10% | 0.1 | 111.56 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 39.04 | |||||
| Total | 1266.17 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 102.66 | ||||
| Grand Total | 1368.83 | |||||||
| Rate per each | 1369 | |||||||
| Rate per each | 1369 | |||||||