Supplying, fitting and fixing of 100 mm floor drain with vertical outlet in traps including making holes in walls/floors and mending good the damages with cement mortar (1:4) etc. all complete approved and accepted by the Engineer- in- charge. of following type.

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 100 mm floor drain with vertical outlet Material cost: (A) 1 no 1050 each 1050 1050
2 Solvent cement Installation cost: (B) Fitting fixing materials: Solvent cement 13.5 ml 0.85 per ml 0.85 11.47
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement mortar (1:4) Cement 0.02 bag 410 per bag 410 8.2
4 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.1 cft 1900 per % cft 19 1.9
5 Plumber Labour: Plumber 0.02 no 700 per day 700 14
6 Skilled labour Skilled labour 0.05 no 600 per day 600 30
Sub-Total 1115.57
Contractor's Profit 10% 0.1 111.56
Contractor's Overhead Expenses 3.5% 0.035 39.04
Total 1266.17
Add VAT with adjustment factor. 1.08108 7.5% 0.075 102.66
Grand Total 1368.83
Rate per each 1369
Rate per each 1369