Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Lever CP Conceal Bib Cock long body with aerator (Oliver/spoon/delta/decent lever or similar) Material: (A) | 1 | no | 850 | each | 850 | 850 | |
| 2 | Teflon Installation cost: (B) Accessories: Teflon tape | 0.3 | no | 17 | per pcs | 17 | 5.1 | |
| 3 | Plumber Labour: Plumber | 0.025 | no | 700 | per day | 700 | 17.5 | |
| 4 | Skilled labour Skilled labour | 0.05 | no | 600 | per day | 600 | 30 | |
| 5 | Ordinary labour Ordinary labour | 0.095 | no | 550 | per day | 550 | 52.25 | |
| Sub-Total | 954.85 | |||||||
| Contractor's Profit | 10% | 0.1 | 95.49 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33.42 | |||||
| Total | 1083.76 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 87.87 | ||||
| Grand Total | 1171.63 | |||||||
| Rate per each | 1172 | |||||||
| Rate per each | 1172 | |||||||