Breakup

26.29.7 CP Leaf Cock

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 CP Leaf Cock Material: (A) 1 no 560 each 560 560
2 Teflon Installation cost: (B) Accessories: Teflon tape 0.3 no 17 per pcs 17 5.1
3 Plumber Labour: Plumber 0.025 no 700 per day 700 17.5
4 Skilled labour Skilled labour 0.05 no 600 per day 600 30
5 Ordinary labour Ordinary labour 0.095 no 550 per day 550 52.25
Sub-Total 664.85
Contractor's Profit 10% 0.1 66.48
Contractor's Overhead Expenses 3.5% 0.035 23.27
Total 754.6
Add VAT with adjustment factor. 1.08108 7.5% 0.075 61.18
Grand Total 815.78
Rate per each 816
Rate per each 816
Help