Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Push Type Self closing pillar cock Material: (A) | 1 | no | 956 | each | 956 | 956 | |
| 2 | Teflon Installation cost: (B) Accessories: Teflon tape | 0.3 | no | 17 | per pcs | 17 | 5.1 | |
| 3 | Plumber Labour: Plumber | 0.03 | no | 700 | per day | 700 | 21 | |
| 4 | Skilled labour Skilled labour | 0.07 | no | 600 | per day | 600 | 42 | |
| 5 | Ordinary labour Ordinary labour | 0.162 | no | 550 | per day | 550 | 89.1 | |
| Sub-Total | 1113.2 | |||||||
| Contractor's Profit | 10% | 0.1 | 111.32 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 38.96 | |||||
| Total | 1263.48 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 102.44 | ||||
| Grand Total | 1365.92 | |||||||
| Rate per each | 1366 | |||||||
| Rate per each | 1366 | |||||||