Breakup

26.34.3 Moving basin mixer

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Moving basin mixer Material: (A) 1 no 2600 each 2600 2600
2 Teflon Installation cost: (B) Accessories: Teflon tape 0.3 no 17 per pcs 17 5.1
3 Plumber Labour: Plumber 0.025 no 700 per day 700 17.5
4 Skilled labour Skilled labour 0.05 no 600 per day 600 30
5 Ordinary labour Ordinary labour 0.095 no 550 per day 550 52.25
Sub-Total 2704.85
Contractor's Profit 10% 0.1 270.49
Contractor's Overhead Expenses 3.5% 0.035 94.67
Total 3070.01
Add VAT with adjustment factor. 1.08108 7.5% 0.075 248.92
Grand Total 3318.93
Rate per each 3319
Rate per each 3319