Breakup

26.38.1 Moving type 100 mm CP shower head

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Moving type 100 mm CP shower head Material: (A) 1 no 915 each 915 915
2 Teflon Installation cost: (B) Accessories: Teflon tape 0.3 no 17 per pcs 17 5.1
3 Plumber Labour:Plumber 0.025 no 700 per day 700 17.5
4 Skilled labour Skilled labour 0.05 no 600 per day 600 30
5 Ordinary labour Ordinary labour 0.095 no 550 per day 550 52.25
Sub-Total 1019.85
Contractor's Profit 10% 0.1 101.99
Contractor's Overhead Expenses 3.5% 0.035 35.69
Total 1157.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 93.85
Grand Total 1251.38
Rate per each 1251
Rate per each 1251