Breakup

01.4.2 Updating the work programme and submission to the Engineer-in-charge at intervals no longer than 28 days showing actual physical and financial progress achieved on each activity and the effect of the progress on the timing of the remaining work, including any changes to the sequence of the activities.However, Engineer’s approval of the programme shall not alter the contractor’s obligations. The contractor may revise the programme and submit it to the Engineer-in-charge again at any time. A revised programme shall show the variations and events related to change of contract price. Month wise documentation shall be the basis of payments on this item.

Updating of implementation schedule prepared in M.S. project software (CPM net working)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Engineer, Expertise in microsoft MS Project /Primavera and experience by min 5yrs Updating implementation schedule prepared in M.S. project software 1 day 150000 permonth 5000 5000
2 printing of drawing Printing : 3 set 12.08 sft 20 sft 20 241.6
Sub-Total 5241.6
Contractor's Profit 10% 0.1 524.16
Contractor's Overhead Expenses 3.5% 0.035 183.46
Total 5949.22
Add VAT with adjustment factor. 1.08108 7.5% 0.075 482.37
Grand Total 6431.59
Rate per each month 6432
Rate per each month 6432