Breakup

26.51.1.1 HDPE pipe of 110 mm outside dia with wall thickness 4.2 mm - 4.8 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 110 mm dia HDPE pipe for under-ground 110 mm dia 20'-0" long pipe: 20 ft 224 per foot 224 4480
2 110 mm HDPE plain Tee/T-Y for under-ground Fittings: 110 mm HDPE Plain Tee/T-Y 0.25 no 835 each 835 208.75
3 110 mm HDPE plain Bend for under-ground 110 mm HDPE Plain Bend 0.5 no 651 each 651 325.5
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials : Butt fusion welding joint 1 gm 430 each 430 430
5 Earthwork in excavation Excavation (underground) 62.5 cft 4979.17 % 0 cft 4.98 311.25
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 38.8 cft 1900 per % cft 19 737.2
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 0.5 no 600 per day 600 300
9 Ordinary labour Ordinary labour 0.8 no 550 per day 550 440
Sub-Total 7582.7
Contractor's Profit 10% 0.1 758.27
Contractor's Overhead Expenses 3.5% 0.035 265.39
Total 8606.36
Add VAT with adjustment factor. 1.08108 7.5% 0.075 697.81
Grand Total 9304.17
Rate per ft 465.2
Rate per meter 1526.32