Breakup

26.51.1.2 HDPE pipe of 160 mm outside dia with wall thickness 6.2 mm - 7.0 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 160 mm dia HDPE pipe for under-ground 160 mm dia 20'-0" long pipe: 20 ft 405 per foot 405 8100
2 160 mm HDPE plain Tee/T-Y for under-ground 160 mm HDPE Plain Tee/T-Y 0.25 no 1195 each 1195 298.75
3 160 mm HDPE plain bend for under-ground 160 mm HDPE Plain Bend 0.5 no 1052 each 1052 526
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 each 430 each 430 430
5 Earthwork in excavation Excavation (underground) 62.5 cft 4979.17 % 0 cft 4.98 311.25
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 38.8 cft 1900 per % cft 19 737.2
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 1 no 600 per day 600 600
9 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 11903.2
Contractor's Profit 10% 0.1 1190.32
Contractor's Overhead Expenses 3.5% 0.035 416.61
Total 13510.13
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1095.41
Grand Total 14605.54
Rate per ft 730.3
Rate per m 2396.11