Considering 20 ft long HDPE one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 160 mm dia HDPE pipe for under-ground 160 mm dia 20'-0" long pipe: | 20 | ft | 405 | per foot | 405 | 8100 | |
| 2 | 160 mm HDPE plain Tee/T-Y for under-ground 160 mm HDPE Plain Tee/T-Y | 0.25 | no | 1195 | each | 1195 | 298.75 | |
| 3 | 160 mm HDPE plain bend for under-ground 160 mm HDPE Plain Bend | 0.5 | no | 1052 | each | 1052 | 526 | |
| 4 | Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint | 1 | each | 430 | each | 430 | 430 | |
| 5 | Earthwork in excavation Excavation (underground) | 62.5 | cft | 4979.17 | % 0 cft | 4.98 | 311.25 | |
| 6 | Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) | 38.8 | cft | 1900 | per % cft | 19 | 737.2 | |
| 7 | Plumber Plumber | 0.5 | no | 700 | per day | 700 | 350 | |
| 8 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 9 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 11903.2 | |||||||
| Contractor's Profit | 10% | 0.1 | 1190.32 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 416.61 | |||||
| Total | 13510.13 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1095.41 | ||||
| Grand Total | 14605.54 | |||||||
| Rate per ft | 730.3 | |||||||
| Rate per m | 2396.11 | |||||||