Breakup

26.51.1.3 HDPE pipe of 200 mm outside dia with wall thickness 7.7 mm - 8.6 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 200 mm dia HDPE pipe for under-ground 200 mm dia 20'-0" long pipe: 20 ft 732 per foot 732 14640
2 200 mm HDPE plain tee/T-Y for under-ground 200 mm HDPE Plain Tee/T-Y 0.25 no 2960 each 2960 740
3 200 mm HDPE plain bend for under-ground 200 mm HDPE Plain Bend 0.5 no 1980 each 1980 990
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 each 430 each 430 430
5 Earthwork in excavation Excavation (underground) 87.5 cft 4979.17 % 0 cft 4.98 435.75
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 52.5 cft 1900 per % cft 19 997.5
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 1 no 600 per day 600 600
9 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 19733.25
Contractor's Profit 10% 0.1 1973.33
Contractor's Overhead Expenses 3.5% 0.035 690.66
Total 22397.24
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1815.99
Grand Total 24213.23
Rate per ft 1210.65
Rate per m 3972.14