Breakup

26.51.1.5 HDPE pipe of 280 mm outside dia with wall thickness 10.7 mm -11.9 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 280 mm dia HDPE pipe for under-ground 280 mm dia 20'-0" long pipe: 20 ft 1427 per foot 1427 28540
2 280 mm HDPE plain tee/T-Y for under-ground 280 mm HDPE Plain Tee/T-Y 0.25 no 7110 each 7110 1777.5
3 280 mm HDPE plain bend for under-ground 280 mm HDPE Plain Bend 0.5 no 5140 each 5140 2570
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 each 430 each 430 430
5 Earthwork in excavation Excavation (underground) 87.5 cft 4979.17 % 0 cft 49.79 4356.63
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 52.5 cft 1900 per % cft 19 997.5
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 1 no 600 per day 600 600
9 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 40171.63
Contractor's Profit 10% 0.1 4017.16
Contractor's Overhead Expenses 3.5% 0.035 1406.01
Total 45594.8
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3696.87
Grand Total 49291.67
Rate per ft 2464.6
Rate per m 8086.35
Help