Breakup

26.51.1.6 HDPE pipe of 315 mm outside dia with wall thickness 12.1 mm -13.5 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 315 mm dia HDPE pipe for under-ground 315 mm dia 20'-0" long pipe: 20 ft 1792 per foot 1792 35840
2 315 mm HDPE plain tee/T-Y for under-ground 315 mm HDPE Plain Tee/T-Y 0.25 no 9512 each 9512 2378
3 315 mm HDPE plain bend for under-ground 315 mm HDPE Plain Bend 0.5 no 7015 each 7015 3507.5
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 each 430 each 430 430
5 Earthwork in excavation Excavation (underground) 87.5 cft 4979.17 % 0 cft 49.79 4356.63
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 52.5 cft 1900 per % cft 19 997.5
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 1 no 600 per day 600 600
9 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 49009.63
Contractor's Profit 10% 0.1 4900.96
Contractor's Overhead Expenses 3.5% 0.035 1715.34
Total 55625.93
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4510.21
Grand Total 60136.14
Rate per ft 3006.8
Rate per m 9865.31