Breakup

26.51.1.7 HDPE pipe of 400 mm outside dia with wall thickness 15.3 mm -17.0 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 400 mm dia HDPE pipe for under-ground 400 mm dia 20'-0" long pipe: 20 ft 2903 per foot 2903 58060
2 400 mm HDPE plain tee/T-Y for under-ground 400 mm HDPE Plain Tee/T-Y 0.25 no 18250 each 18250 4562.5
3 400 mm HDPE plain bend for under-ground 400 mm HDPE Plain Bend 0.5 no 14010 each 14010 7005
4 Butt fusion welding joint(400-560 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 each 540 each 540 540
5 Earthwork in excavation Excavation (underground) 87.5 cft 4979.17 % 0 cft 49.79 4356.63
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 52.5 cft 1900 per % cft 19 997.5
7 Plumber Plumber 1 no 700 per day 700 700
8 Skilled labour Skilled labour 0.25 no 600 per day 600 150
9 Ordinary labour Ordinary labour 2 no 550 per day 550 1100
Sub-Total 77471.63
Contractor's Profit 10% 0.1 7747.16
Contractor's Overhead Expenses 3.5% 0.035 2711.51
Total 87930.3
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7129.48
Grand Total 95059.78
Rate per ft 4753
Rate per m 15594.59