26.51.1.8 HDPE pipe of 630 mm outside dia with wall thickness 24.2 mm - 26.7 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 630 mm dia HDPE pipe for under-ground 630 mm dia 20'-0" long pipe: 20 ft 6800 per foot 6800 136000
2 630 mm HDPE plain tee/T-Y for under-ground 630 mm HDPE Plain Tee/T-Y 0.25 no 51000 each 51000 12750
3 630 mm HDPE plain bend for under-ground 630 mm HDPE Plain Bend 0.5 no 40100 each 40100 20050
4 Butt fusion welding joint(630-1000 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 no 710 each 710 710
5 Earthwork in excavation Excavation (underground) 112.5 cft 4979.17 % 0 cft 49.79 5601.38
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 77.5 cft 1900 per % cft 19 1472.5
7 Plumber Plumber 1 no 700 per day 700 700
8 Skilled labour Skilled labour 0.25 no 600 per day 600 150
9 Ordinary labour Ordinary labour 3 nos 550 per day 550 1650
Sub-Total 179083.88
Contractor's Profit 10% 0.1 17908.39
Contractor's Overhead Expenses 3.5% 0.035 6267.94
Total 203260.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 16480.54
Grand Total 219740.75
Rate per ft 10987.05
Rate per m 36048.51