Breakup

26.51.1.10 HDPE pipe of 900 mm outside dia with wall thickness 34.4 mm - 38.3 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 900 mm dia HDPE pipe for under-ground 900 mm dia 20'-0" long pipe: 20 ft 13100 per foot 13100 262000
2 900 mm HDPE plain Tee/T-Y for under-ground 900 mm HDPE Plain Tee/T-Y 0.25 no 108000 each 108000 27000
3 900 mm HDPE plain bend for under-ground 900 mm HDPE Plain Bend 0.5 no 85000 each 85000 42500
4 Butt fusion welding joint(630-1000 mm dia HDPE pipe) Jointing & fixing Materials Butt fusion welding joint 1 no 710 each 710 710
5 Earthwork in excavation Excavation (underground) 112.5 cft 4979.17 % 0 cft 49.79 5601.38
6 Sand (F.M. 1.2) Bedding by sand (FM 0.8) (underground) 77.5 cft 1900 per % cft 19 1472.5
7 Plumber Plumber 1 no 700 per day 700 700
8 Skilled labour Skilled labour 0.25 no 600 per day 600 150
9 Ordinary labour Ordinary labour 3 nos 550 per day 550 1650
Sub-Total 341783.88
Contractor's Profit 10% 0.1 34178.39
Contractor's Overhead Expenses 3.5% 0.035 11962.44
Total 387924.71
Add VAT with adjustment factor. 1.08108 7.5% 0.075 31453.32
Grand Total 419378.03
Rate per ft 20968.9
Rate per m 68798.96