Breakup

26.51.2.1 HDPE pipe 110 mm outside dia with wall thickness 4.2 mm - 4.8 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 110 mm dia HDPE pipe 110 mm dia 20'-0" long pipe: 20 ft 221 per foot 221 4420
2 110 mm HDPE plain tee/T-Y Fittings: 110 mm HDPE Plain Tee/T-Y 1.2 no 1650 each 1650 1980
3 110 mm HDPE plain bend 110 mm HDPE Plain Bend 1.8 no 1155 each 1155 2079
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials : Electro fusion welding joint 1 no 430 each 430 430
5 Plumber Labour: Plumber 0.5 no 700 per day 700 350
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 0.8 no 550 per day 550 440
Sub-Total 9999
Contractor's Profit 10% 0.1 999.9
Contractor's Overhead Expenses 3.5% 0.035 349.97
Total 11348.87
Add VAT with adjustment factor. 1.08108 7.5% 0.075 920.18
Grand Total 12269.05
Rate per ft 613.45
Rate per meter 2012.73