Breakup

26.51.2.2 HDPE pipe 160 mm outside dia with wall thickness 6.2 mm -7.0 mm

Considering 20 ft long HDPE one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 160 mm dia HDPE pipe 160 mm dia 20'-0" long pipe: 20 ft 405 per foot 405 8100
2 160 mm HDPE plain tee/T-Y Fittings: 160 mm HDPE Plain Tee/T-Y 1.2 no 2520 each 2520 3024
3 160 mm HDPE plain bend 160 mm HDPE Plain Bend 1.8 no 1790 each 1790 3222
4 Butt fusion welding joint(75-355 mm dia HDPE pipe) Jointing & fixing Materials : Electro fusion welding joint 1 no 430 each 430 430
5 Plumber Labour: Plumber 0.5 no 700 per day 700 350
6 Skilled labour Skilled labour 1 no 600 per day 600 600
7 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 16276
Contractor's Profit 10% 0.1 1627.6
Contractor's Overhead Expenses 3.5% 0.035 569.66
Total 18473.26
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1497.83
Grand Total 19971.09
Rate per ft 998.55
Rate per meter 3276.24
Help