04.22.3 50 mm thick brick pavement with 200 mm x 50 mm x 50 mm klinker facing bricks.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 8" x 2" x 2"/ 200 x 50 x 50 mm machine made klinker facing red or maroon strips 200 x 50 x 50 mm klinker paving bricks (facing 200 x 50 mm)in/c 5% wastage 856 nos 18000 per % 0 nos 18 15408
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 13 cft 1900 per % cft 19 247
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement (in/c for flush pointing) 2.5 bags 410 per bag 410 1025
4 Head mason / Mosaic head mistry Head mason 0.25 no 800 per day 800 200
5 Mason / Mosaic mistry Mason 1.25 nos 700 per day 700 875
6 Skilled labour Skilled labour 2.5 nos 600 per day 600 1500
7 Ordinary labour Ordinary labour 1.5 nos 550 per day 550 825
8 Ordinary labour Labour for soaking & cleaning bricks 1 no 550 per day 550 550
9 Ordinary labour Labour for 7 days curing @ 1/8 labour per day. 0.875 no 550 per day 550 481.25
10 Ordinary labour Local carriage & storage, sundries etc. 1 LS 550 per day 275 275
Sub-Total 21386.25
Contractor's Profit 10% 0.1 2138.63
Contractor's Overhead Expenses 3.5% 0.035 748.52
Total 24273.4
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1968.11
Grand Total 26241.51
Rate per sft 262.42
Rate per per sqm 2824.82