Considering 20 ft long one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 mm dia GI pipe 12 mm dia G.I. pipe: | 20 | ft | 68 | per foot | 68 | 1360 | |
| 2 | 12 mm dia elbow Fittings: Elbow | 1 | no | 28 | each | 28 | 28 | |
| 3 | 12 mm dia tee Tee | 1 | no | 35 | each | 35 | 35 | |
| 4 | 12 mm dia nipple Nipple | 1 | no | 23 | each | 23 | 23 | |
| 5 | 12 mm dia plug Plug | 1 | no | 12 | each | 12 | 12 | |
| 6 | 12 mm dia socket Socket | 1 | no | 18.5 | each | 18.5 | 18.5 | |
| 7 | Teflon Jointing & fixing materials : Teflon tape | 2.1 | pcs | 17 | per pcs | 17 | 35.7 | |
| 8 | Clamp Clamp | 2 | nos | 40 | each | 40 | 80 | |
| 9 | 50 mm screw & rowel plug Rowel plug & screw | 4 | nos | 9 | each | 9 | 36 | |
| 10 | Scaffolding Scaffolding | 20 | ft | 3.5 | per foot | 3.5 | 70 | |
| 11 | Plumber Labour: Plumber | 0.125 | no | 700 | per day | 700 | 87.5 | |
| 12 | Skilled labour Skilled labour | 0.375 | no | 600 | per day | 600 | 225 | |
| 13 | Ordinary labour Ordinary labour | 0.325 | no | 550 | per day | 550 | 178.75 | |
| Sub-Total | 2189.45 | |||||||
| Contractor's Profit | 10% | 0.1 | 218.94 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 76.63 | |||||
| Total | 2485.02 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 201.49 | ||||
| Grand Total | 2686.51 | |||||||
| Rate per ft | 134.35 | |||||||
| Rate per meter | 440.8 | |||||||