Considering 20 ft long one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm dia GI pipe 25 mm dia G.I. pipe: | 20 | ft | 121 | per foot | 121 | 2420 | |
| 2 | 25 mm dia elbow Fittings: Elbow | 1 | no | 65 | each | 65 | 65 | |
| 3 | 25 mm dia tee Tee | 1 | no | 70 | each | 70 | 70 | |
| 4 | 25 mm dia nipple Nipple | 1 | no | 45 | each | 45 | 45 | |
| 5 | 25 mm dia plug Plug | 1 | no | 25 | each | 25 | 25 | |
| 6 | 25 mm dia reducer Reducer | 1 | no | 45 | each | 45 | 45 | |
| 7 | 25 mm dia socket Socket | 1 | no | 40 | each | 40 | 40 | |
| 8 | Teflon Jointing & fixing materials : Teflon tape | 4.2 | pcs | 17 | per pcs | 17 | 71.4 | |
| 9 | Clamp Clamp | 2 | nos | 40 | each | 40 | 80 | |
| 10 | 50 mm screw & rowel plug Rowel plug & screw | 4 | nos | 9 | each | 9 | 36 | |
| 11 | Scaffolding Scaffolding | 20 | ft | 3.5 | per foot | 3.5 | 70 | |
| 12 | Plumber Labour: Plumber | 0.125 | no | 700 | per day | 700 | 87.5 | |
| 13 | Skilled labour Skilled labour | 0.25 | no | 600 | per day | 600 | 150 | |
| 14 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| Sub-Total | 3479.9 | |||||||
| Contractor's Profit | 10% | 0.1 | 347.99 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 121.8 | |||||
| Total | 3949.69 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 320.24 | ||||
| Grand Total | 4269.93 | |||||||
| Rate per ft | 213.5 | |||||||
| Rate per meter | 700.49 | |||||||