Considering 20 ft long one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 150 mm dia uPVC Pipe: 20 foot (6m) long 150 mm dia 20'-0" long pipe: | 20 | ft | 263 | per foot | 263 | 5260 | |
| 2 | 150 mm dia uPVC bend/offset/cowl Fittings: Bend/45O bend/off-set/cowel etc. | 1 | no | 375 | each | 375 | 375 | |
| 3 | 150 mm dia uPVC Tee/T-Y/Y (50 x 50 mm) Tee/T-Y/Y | 1 | no | 403 | each | 403 | 403 | |
| 4 | Solvent cement Jointing & fixing materials : Solvent cement | 120 | ml | 0.85 | per ml | 0.85 | 102 | |
| 5 | Clamp Clamp | 4 | no | 40 | each | 40 | 160 | |
| 6 | 50 mm screw & rowel plug Rowel plug & screw | 8 | nos | 9 | each | 9 | 72 | |
| 7 | Scaffolding Scaffolding | 20 | ft | 3.5 | per foot | 3.5 | 70 | |
| 8 | Plumber Labour: Plumber | 0.5 | no | 700 | per day | 700 | 350 | |
| 9 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 10 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 7942 | |||||||
| Contractor's Profit | 10% | 0.1 | 794.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 277.97 | |||||
| Total | 9014.17 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 730.88 | ||||
| Grand Total | 9745.05 | |||||||
| Rate per ft | 487.25 | |||||||
| Rate per meter | 1598.67 | |||||||