Breakup

150 mm inside dia wall thickness 4.5 mm - 5.2 mm

Considering 20 ft long one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 150 mm dia uPVC Pipe: 20 foot (6m) long 150 mm dia 20'-0" long pipe: 20 ft 263 per foot 263 5260
2 150 mm dia uPVC bend/offset/cowl Fittings: Bend/45O bend/off-set/cowel etc. 1 no 375 each 375 375
3 150 mm dia uPVC Tee/T-Y/Y (50 x 50 mm) Tee/T-Y/Y 1 no 403 each 403 403
4 Solvent cement Jointing & fixing materials : Solvent cement 120 ml 0.85 per ml 0.85 102
5 Clamp Clamp 4 no 40 each 40 160
6 50 mm screw & rowel plug Rowel plug & screw 8 nos 9 each 9 72
7 Scaffolding Scaffolding 20 ft 3.5 per foot 3.5 70
8 Plumber Labour: Plumber 0.5 no 700 per day 700 350
9 Skilled labour Skilled labour 1 no 600 per day 600 600
10 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 7942
Contractor's Profit 10% 0.1 794.2
Contractor's Overhead Expenses 3.5% 0.035 277.97
Total 9014.17
Add VAT with adjustment factor. 1.08108 7.5% 0.075 730.88
Grand Total 9745.05
Rate per ft 487.25
Rate per meter 1598.67
Help