Breakup

200 mm dia with wall thickness 5.3 mm - 7.8 mm uPVC pipe

Considering 20 ft long one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 200 mm dia uPVC pipe for under-ground 200 mm uPVC pipe: 20 ft 402 per foot 402 8040
2 Solvent cement Solvent cement 50 ml 0.85 per ml 0.85 42.5
3 Earthwork in excavation Excavation 87.5 cft 4979.17 % 0 cft 4.98 435.75
4 Sand (F.M. 1.2) Bedding by sand (F.M. 0.8) 67.5 cft 1900 per % cft 19 1282.5
5 Plumber Plumber 0.25 no 700 per day 700 175
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 10550.75
Contractor's Profit 10% 0.1 1055.08
Contractor's Overhead Expenses 3.5% 0.035 369.28
Total 11975.11
Add VAT with adjustment factor. 1.08108 7.5% 0.075 970.95
Grand Total 12946.06
Rate per ft 647.3
Rate per m 2123.79