Breakup

04.24 125 mm thick brick pavement/flooring with 10 hole machine made ceramic bricks with cement sand (F.M. 1.2) mortar (1:4) on minimum 12 mm thick cement sand (F.M. 1.2) mortar (1:4) including cutting the bricks as per requirement, cleaning and racking out joints, finishing with flush pointing with cement sand (F.M. 1.2) mortar (1:2) and curing for at least 7 days etc. including cost of water, washing and screening of sand (F.M. 1.2), electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M)

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class 10 holes machine made 9.5" x 4.5" x 2.75" / 237.5 mm x 112.5 mm x 68.75 mm size ceramic bricks 10 holes ceramic bricks 480 nos 19900 per % 0 nos 19.9 9552
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 16 cft 1900 per % cft 19 304
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement (in/c for flush pointing) 3.25 bags 410 per bag 410 1332.5
4 Head mason / Mosaic head mistry Head mason 0.25 no 800 per day 800 200
5 Mason / Mosaic mistry Mason 1.25 nos 700 per day 700 875
6 Skilled labour Skilled labour 2.25 nos 600 per day 600 1350
7 Ordinary labour Ordinary labour 1.5 nos 550 per day 550 825
8 Ordinary labour Labour for soaking & cleaning bricks 0.5 no 550 per day 550 275
9 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day 0.875 no 550 per day 550 481.25
10 Ordinary labour Local carriage, storage & sundries etc. 1 LS 550 per day 275 275
Sub-Total 15469.75
Contractor's Profit 10% 0.1 1546.98
Contractor's Overhead Expenses 3.5% 0.035 541.44
Total 17558.17
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1423.63
Grand Total 18981.8
Rate per sft 189.82
Rate per per sqm 2043.32