Breakup

280 mm dia with wall thickness 6.9 mm - 8.6 mm uPVC pipe

Considering 20 ft long one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 280 mm dia uPVC pipe for under-ground 280 mm uPVC pipe: 20 ft 723 per foot 723 14460
2 Solvent cement Solvent cement 330 ml 0.85 per ml 0.85 280.5
3 Earthwork in excavation Excavation 87.5 cft 4979.17 % 0 cft 4.98 435.75
4 Sand (F.M. 1.2) Bedding by sand (F.M. 0.8) 52.5 cft 1900 per % cft 19 997.5
5 Plumber Plumber 0.25 no 700 per day 700 175
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 17198.75
Contractor's Profit 10% 0.1 1719.88
Contractor's Overhead Expenses 3.5% 0.035 601.96
Total 19520.59
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1582.75
Grand Total 21103.34
Rate per ft 1055.15
Rate per m 3461.95