Considering 20 ft long 6 nos pipe = 120 ft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 mm dia uPVC pipe 12 mm dia uPVC pipe | 120 | ft | 12.75 | per foot | 12.75 | 1530 | |
| 2 | 12 mm dia uPVC plain Tee Fittings:12 mm uPVC plain Tee | 10 | nos | 10 | each | 10 | 100 | |
| 3 | 12 mm dia uPVC plain elbow 12 mm uPVC plain elbow | 25 | nos | 8 | each | 8 | 200 | |
| 4 | 12 mm dia uPVC faucet elbow 12 mm uPVC faucet elbow | 5 | nos | 10 | each | 10 | 50 | |
| 5 | 12 mm dia uPVC plain socket 12 mm uPVC plain socket | 6 | nos | 7.5 | each | 7.5 | 45 | |
| 6 | 12 mm dia uPVC thread plug 12 mm uPVC thread plug | 5 | nos | 5.2 | each | 5.2 | 26 | |
| 7 | Solvent cement Jointing & fixing materials : Solvent cement for jointing | 50 | ml | 0.85 | per ml | 0.85 | 42.5 | |
| 8 | Plumber Plumber | 1 | no | 700 | per day | 700 | 700 | |
| 9 | Skilled labour Skilled labour | 2 | no | 600 | per day | 600 | 1200 | |
| 10 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| Sub-Total | 4993.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 499.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 174.77 | |||||
| Total | 5667.62 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 459.54 | ||||
| Grand Total | 6127.16 | |||||||
| Rate per ft | 51.06 | |||||||
| Rate per meter | 167.53 | |||||||