Considering 20 ft long 3.5 nos pipe = 70 ft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 19 mm dia uPVC pipe 19 mm dia uPVC pipe | 70 | ft | 17 | per foot | 17 | 1190 | |
| 2 | 19 mm dia uPVC plain tee Fittings: 19 mm uPVC plain Tee | 5 | nos | 13.2 | each | 13.2 | 66 | |
| 3 | 19 mm dia uPVC plain elbow 19 mm uPVC plain elbow | 10 | nos | 12.5 | each | 12.5 | 125 | |
| 4 | 19 mm dia uPVC plain socket 19 mm uPVC plain socket | 4 | nos | 8 | each | 8 | 32 | |
| 5 | 19mm x 12 mm dia uPVC reduced tee 19 x 12 mm uPVC round Tee | 5 | nos | 30 | each | 30 | 150 | |
| 6 | 19mm x 12 mm dia uPVC reduced elbow 19 x 12 mm uPVC round elbow | 10 | nos | 30 | each | 30 | 300 | |
| 7 | Solvent cement Jointing & fixing materials : Solvent cement | 50 | ml | 0.85 | per ml | 0.85 | 42.5 | |
| 8 | Plumber Labour: Plumber | 1 | no | 700 | per day | 700 | 700 | |
| 9 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 10 | Ordinary labour Labour | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 3755.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 375.55 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 131.44 | |||||
| Total | 4262.49 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 345.61 | ||||
| Grand Total | 4608.1 | |||||||
| Rate per ft | 65.83 | |||||||
| Rate per meter | 215.99 | |||||||