Breakup

75 mm dia wall thickness 2.9 mm - 3.5 mm

Considering 1 piece of 20 rft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75 mm dia uPVC pipe 75 mm dia pipe 20 ft 80 per foot 80 1600
2 75 mm dia tee Fittings: 75 mm Tee 1 no 210 each 210 210
3 75 mm dia socket 75 mm socket 2 nos 90 each 90 180
4 75 mm dia elbow 75 mm elbow 2 nos 180 each 180 360
5 Solvent cement Jointing & fixing materials : Solvent cement 70 ml 0.85 per ml 0.85 59.5
6 Plumber Labour: Plumber 0.5 no 700 per day 700 350
7 Skilled labour Plumber helper 0.5 no 600 per day 600 300
8 Ordinary labour Local carriage, sundries etc. 1 LS 550 per day 110 110
Sub-Total 3169.5
Contractor's Profit 10% 0.1 316.95
Contractor's Overhead Expenses 3.5% 0.035 110.93
Total 3597.38
Add VAT with adjustment factor. 1.08108 7.5% 0.075 291.68
Grand Total 3889.06
Rate per rft 194.45
Rate per meter 637.99