Breakup

04.25 75 mm thick cement concrete (1:3:6) flooring with cement, best quality coarse sand and 19 mm down graded picked jhama brick chips including breaking of chips, screening, mixing, laying, compacting, washing and screening of sand (F.M 1.2) and curing at least for 7 days etc. including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M)

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 (1:3:6) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete 100 cft 14983 % cft 37.46 3746
2 Mason / Mosaic mistry Add extra for floor casting: 1 no 700 per day 700 700
Sub-Total 4446
Contractor's Profit 10% 0.1 444.6
Contractor's Overhead Expenses 3.5% 0.035 155.61
Total 5046.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 409.15
Grand Total 5455.36
Rate per sft 54.55
Rate per sqm 587.18
Help