Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | (1:3:6) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete | 100 | cft | 14983 | % cft | 37.46 | 3746 | |
| 2 | Mason / Mosaic mistry Add extra for floor casting: | 1 | no | 700 | per day | 700 | 700 | |
| Sub-Total | 4446 | |||||||
| Contractor's Profit | 10% | 0.1 | 444.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 155.61 | |||||
| Total | 5046.21 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 409.15 | ||||
| Grand Total | 5455.36 | |||||||
| Rate per sft | 54.55 | |||||||
| Rate per sqm | 587.18 | |||||||