Considering 20 ft long one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 88 mm dia uPVC pipe 88 mm dia pipe | 20 | ft | 94 | per foot | 94 | 1880 | |
| 2 | 88 mm dia tee Fittings: 88 mm Tee | 1 | no | 225 | each | 225 | 225 | |
| 3 | 88 mm dia socket 88 mm socket | 2 | nos | 135 | each | 135 | 270 | |
| 4 | 88 mm dia elbow 88 mm elbow | 2 | nos | 192 | each | 192 | 384 | |
| 5 | Solvent cement Jointing & fixing materials : Solvent cement | 100 | ml | 0.85 | per ml | 0.85 | 85 | |
| 6 | Plumber Labour: Plumber | 0.5 | no | 700 | per day | 700 | 350 | |
| 7 | Skilled labour Plumber helper | 0.5 | no | 600 | per day | 600 | 300 | |
| 8 | Ordinary labour Local carriage, sundries etc. | 1 | LS | 550 | per day | 154 | 154 | |
| Sub-Total | 3648 | |||||||
| Contractor's Profit | 10% | 0.1 | 364.8 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 127.68 | |||||
| Total | 4140.48 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 335.71 | ||||
| Grand Total | 4476.19 | |||||||
| Rate per ft | 223.8 | |||||||
| Rate per meter | 734.29 | |||||||