Considering 20 ft long one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 114 mm dia uPVC pipe 114 mm dia pipe | 20 | ft | 125 | per foot | 125 | 2500 | |
| 2 | 114 mm dia tee Fittings: 114 mm Tee | 1 | no | 320 | each | 320 | 320 | |
| 3 | 114 mm dia socket 114 mm socket | 2 | nos | 160 | each | 160 | 320 | |
| 4 | 114 mm dia elbow 114 mm elbow | 2 | nos | 202 | each | 202 | 404 | |
| 5 | Solvent cement Jointing & fixing materials : Solvent cement | 140 | ml | 0.85 | per ml | 0.85 | 119 | |
| 6 | Plumber Labour: Plumber | 0.5 | no | 700 | per day | 700 | 350 | |
| 7 | Skilled labour Plumber helper | 0.5 | no | 600 | per day | 600 | 300 | |
| 8 | Ordinary labour Local carriage, sundries etc. | 1 | LS | 550 | per day | 154 | 154 | |
| Sub-Total | 4467 | |||||||
| Contractor's Profit | 10% | 0.1 | 446.7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 156.35 | |||||
| Total | 5070.05 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 411.08 | ||||
| Grand Total | 5481.13 | |||||||
| Rate per ft | 274.05 | |||||||
| Rate per meter | 899.16 | |||||||