Considering 20 ft long 6 nos pipe = 120 ft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 mm dia CPVC pipe 12 mm dia CPVC pipe | 120 | ft | 27 | per foot | 27 | 3240 | |
| 2 | 12 mm dia CPVC plain tee Fittings: 12 mm CPVC plain Tee | 10 | nos | 36 | each | 36 | 360 | |
| 3 | 12 mm dia CPVC plain elbow 12 mm CPVC plain elbow | 25 | nos | 28 | each | 28 | 700 | |
| 4 | 12 mm dia CPVC faucet elbow 12 mm CPVC faucet elbow | 5 | nos | 26 | each | 26 | 130 | |
| 5 | 12 mm dia CPVC plain socket 12 mm CPVC plain socket | 6 | nos | 20 | each | 20 | 120 | |
| 6 | 12 mm dia CPVC thread plug 12 mm CPVC thread plug | 5 | nos | 6 | each | 6 | 30 | |
| 7 | Solvent cement Jointing & fixing materials : Solvent cement for jointing | 400 | ml | 0.85 | per ml | 0.85 | 340 | |
| 8 | Plumber Labour: Plumber | 1 | no | 700 | per day | 700 | 700 | |
| 9 | Skilled labour Skilled labour | 2 | nos | 600 | per day | 600 | 1200 | |
| 10 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| Sub-Total | 7920 | |||||||
| Contractor's Profit | 10% | 0.1 | 792 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 277.2 | |||||
| Total | 8989.2 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 728.85 | ||||
| Grand Total | 9718.05 | |||||||
| Rate per ft | 80.98 | |||||||
| Rate per meter | 265.7 | |||||||