Considering 20 ft long 3.5 nos pipe = 70 ft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 19 mm dia CPVC pipe 19 mm dia CPVC pipe | 70 | ft | 42 | per foot | 42 | 2940 | |
| 2 | 19 mm dia CPVC plain tee Fittings: 19 mm CPVC plain Tee | 5 | nos | 58 | each | 58 | 290 | |
| 3 | 19 mm dia CPVC plain elbow 19 mm CPVC plain elbow | 10 | nos | 55 | each | 55 | 550 | |
| 4 | 19 mm dia CPVC plain socket 19 mm CPVC plain socket | 4 | nos | 18 | each | 18 | 72 | |
| 5 | 19mm x 12 mm dia CPVC reduced tee 19 x 12 mm CPVC round Tee | 5 | nos | 80 | each | 80 | 400 | |
| 6 | 19mm x 12 mm dia CPVC reduced elbow 19 x 12 mm CPVC round elbow | 10 | nos | 58 | each | 58 | 580 | |
| 7 | Solvent cement Jointing & fixing materials : Solvent cement | 50 | ml | 0.85 | per ml | 0.85 | 42.5 | |
| 8 | Plumber Labour: Plumber | 1 | no | 700 | per day | 700 | 700 | |
| 9 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 10 | Ordinary labour Labour | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 6724.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 672.45 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 235.36 | |||||
| Total | 7632.31 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 618.84 | ||||
| Grand Total | 8251.15 | |||||||
| Rate per ft | 117.87 | |||||||
| Rate per meter | 386.73 | |||||||