Breakup

25 mm dia wall thickness 3.4 mm - 4.0 mm

Considering 20 ft long one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 25 mm dia CPVC pipe 25 mm dia CPVC pipe 20 ft 60 per foot 60 1200
2 25 mm x 19 mm dia redeuced Tee Fittings: 25 x 19 mm round. Tee 2 nos 141 each 141 282
3 Solvent cement Jointing & fixing materials : Solvent cement 25 ml 0.85 per ml 0.85 21.25
4 Plumber Labour: Plumber 0.25 no 700 per day 700 175
5 Skilled labour Skilled labour 0.5 no 600 per day 600 300
6 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 2253.25
Contractor's Profit 10% 0.1 225.33
Contractor's Overhead Expenses 3.5% 0.035 78.86
Total 2557.44
Add VAT with adjustment factor. 1.08108 7.5% 0.075 207.36
Grand Total 2764.8
Rate per ft 138.25
Rate per meter 453.6