Breakup

19 mm dia, minimum wall thickness 3.5 mm

Considering 20 ft Long one pipe

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 3/4" PP-R pipe (minimum wall thickness 3.5 mm) 3/4" Dia PP-R Pipe 20 ft 23.75 per foot 23.75 475
2 3/4" PP-R elbow Fittings: Elbow 1 no 11.4 each 11.4 11.4
3 3/4" PP-R tee Tee 1 no 15 each 15 15
4 3/4" PP-R end cap End Cap 1 no 11.5 each 11.5 11.5
5 3/4" PP-R plug Plug 1 no 8.55 each 8.55 8.55
6 3/4" PP-R reducer Reducer 1 no 29 each 29 29
7 3/4" PP-R socket Socket 1 no 8.5 each 8.5 8.5
8 Teflon Jointing & fixing Materials : Teflon Tape 2 pcs 17 per pcs 17 34
9 Clamp Clamp (F.I. Bar) 2 nos 40 each 40 80
10 50 mm screw & rowel plug Rowel Plug & screw 4 nos 9 each 9 36
11 Scaffolding Scaffolding 20 ft 3.5 per foot 3.5 70
12 Plumber Labour: Plumber 0.25 no 700 per day 700 175
13 Skilled labour Skilled labour 0.5 no 600 per day 600 300
14 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 1803.95
Contractor's Profit 10% 0.1 180.4
Contractor's Overhead Expenses 3.5% 0.035 63.14
Total 2047.49
Add VAT with adjustment factor. 1.08108 7.5% 0.075 166.01
Grand Total 2213.5
Rate per ft 110.7
Rate per meter 363.21