Considering 20 ft Long one pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 1.25" PP-R pipe (minimum wall thickness 5.5 mm) 1.25" Dia PP-R Pipe | 20 | ft | 57 | per foot | 57 | 1140 | |
| 2 | 1.25" PP-R elbow Fittings: Elbow | 1 | no | 60 | each | 60 | 60 | |
| 3 | 1.25" PP-R tee Tee | 1 | no | 62 | each | 62 | 62 | |
| 4 | 1.25" PP-R end cap End Cap | 1 | no | 38 | each | 38 | 38 | |
| 5 | 1.25" PP-R plug Plug | 1 | no | 37 | each | 37 | 37 | |
| 6 | 1.25" PP-R reducer Reducer | 1 | no | 67.5 | each | 67.5 | 67.5 | |
| 7 | 1.25" PP-R socket Socket | 1 | no | 24 | each | 24 | 24 | |
| 8 | Teflon Jointing & fixing Materials : Teflon Tape | 2 | pcs | 17 | per pcs | 17 | 34 | |
| 9 | Clamp Clamp (F.I. Bar) | 2 | nos | 40 | each | 40 | 80 | |
| 10 | 50 mm screw & rowel plug Rowel Plug & screw | 4 | nos | 9 | each | 9 | 36 | |
| 11 | Scaffolding Scaffolding | 20 | ft | 3.5 | per foot | 3.5 | 70 | |
| 12 | Plumber Labour: Plumber | 0.25 | no | 700 | per day | 700 | 175 | |
| 13 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 14 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| Sub-Total | 2673.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 267.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 93.57 | |||||
| Total | 3034.42 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 246.03 | ||||
| Grand Total | 3280.45 | |||||||
| Rate per ft | 164 | |||||||
| Rate per meter | 538.08 | |||||||