Breakup

R.C.C pipe of 150 mm dia with thickness 40mm

Considering 1.83 m long 3 nos pipe = 5.49 m work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 150 mm dia RCC pipe (stone-chips, 40 mm thickness. 6'-0" long) 150 mm dia 1.83 m long RCC pipe: 3 nos 1160 each (6'-0") 1160 3480
2 Hem Hem 1.35 sqm 32 per sqm 32 43.2
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 0.2 bag 410 per bag 410 82
4 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.52 cft 1900 per % cft 19 9.88
5 Earthwork in excavation excavation 72.75 cft 4979.17 % 0 cft 4.98 362.3
6 Sand (F.M. 1.2) Bedding by sand (F.M. 1.2) 12.78 cft 1900 per % cft 19 242.82
7 Plumber Plumber 0.25 no 700 per day 700 175
8 Skilled labour Skilled labour 0.5 no 600 per day 600 300
9 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 4970.2
Contractor's Profit 10% 0.1 497.02
Contractor's Overhead Expenses 3.5% 0.035 173.96
Total 5641.18
Add VAT with adjustment factor. 1.08108 7.5% 0.075 457.39
Grand Total 6098.57
Rate per m 1110.93
Rate per m 1110.93