Breakup

R.C.C pipe of 300 mm dia with thickness 50mm

Considering 1.83 m long 3 nos pipe = 5.49 m work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 300 mm dia RCC pipe (stone-chips, 50 mm thickness. 6'-0" long) 300 mm dia 1.83 m long RCC pipe: 3 nos 3210 each (6'-0") 3210 9630
2 Hem Hem 2.19 sqm 32 per sqm 32 70.08
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 0.4 bag 410 per bag 410 164
4 Sand (F.M. 1.2) Sand (F.M. 1.2) 1 cft 1900 per % cft 19 19
5 Earthwork in excavation Excavation 175.16 cft 4979.17 % 0 cft 4.98 872.3
6 Sand (F.M. 1.2) Bedding by sand (F.M. 1.2) 21.96 cft 1900 per % cft 19 417.24
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 0.5 no 600 per day 600 300
9 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
Sub-Total 12922.62
Contractor's Profit 10% 0.1 1292.26
Contractor's Overhead Expenses 3.5% 0.035 452.29
Total 14667.17
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1189.23
Grand Total 15856.4
Rate per m 2888.16
Rate per m 2888.16