Breakup

R.C.C pipe of 375 mm dia with thickness 50mm

Considering 1.83 m long 3 nos pipe = 5.49 m work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 375 mm dia RCC pipe (stone-chips, 50 mm thickness. 6'-0" long) 375 mm dia 1.83 m long RCC pipe: 3 nos 4150 each (6'-0") 4150 12450
2 Hem Hem 2.73 sqm 32 per sqm 32 87.36
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 0.47 bag 410 per bag 410 192.7
4 Sand (F.M. 1.2) Sand (F.M. 1.2) 1.18 cft 1900 per % cft 19 22.42
5 Earthwork in excavation Excavation 217.89 cft 4979.17 % 0 cft 4.98 1085.09
6 Sand (F.M. 1.2) Bedding by sand (F.M. 1.2) 26.3 cft 1900 per % cft 19 499.7
7 Plumber Plumber 0.5 no 700 per day 700 350
8 Skilled labour Skilled labour 1 no 600 per day 600 600
9 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
Sub-Total 16387.27
Contractor's Profit 10% 0.1 1638.73
Contractor's Overhead Expenses 3.5% 0.035 573.55
Total 18599.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1508.07
Grand Total 20107.62
Rate per m 3662.66
Rate per m 3662.66