Breakup

12 mm PP-R Union

Considering 1no. Of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1/2" PP-R union 1/2" PP-R Union 1 no 135 each 135 135
2 Teflon Fittings fixing materials: Teflon Tape 2 pcs 17 per pcs 17 34
3 Plumber Labour: Plumber 0.025 no 700 per day 700 17.5
4 Skilled labour Skilled labour 0.075 no 600 per day 600 45
5 Ordinary labour Ordinary labour 0.05 no 550 per day 550 27.5
Sub-Total 259
Contractor's Profit 10% 0.1 25.9
Contractor's Overhead Expenses 3.5% 0.035 9.07
Total 293.97
Add VAT with adjustment factor. 1.08108 7.5% 0.075 23.84
Grand Total 317.81
Rate per each 318
Rate per each 318