Breakup

19 mm PP-R Union

Considering 1no. Of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 3/4" PP-R union 3/4" PP-R Union 1 no 160 each 160 160
2 Teflon Fittings fixing materials: Teflon Tape 2 pcs 17 per pcs 17 34
3 Plumber Labour: Plumber 0.03 no 700 per day 700 21
4 Skilled labour Skilled labour 0.08 no 600 per day 600 48
5 Ordinary labour Ordinary labour 0.06 no 550 per day 550 33
Sub-Total 296
Contractor's Profit 10% 0.1 29.6
Contractor's Overhead Expenses 3.5% 0.035 10.36
Total 335.96
Add VAT with adjustment factor. 1.08108 7.5% 0.075 27.24
Grand Total 363.2
Rate per each 363
Rate per each 363