Considering 1no. Of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 1" PP-R union 1" PP-R Union | 1 | no | 178 | each | 178 | 178 | |
| 2 | Teflon Fittings fixing materials: Teflon Tape | 2 | pcs | 17 | per pcs | 17 | 34 | |
| 3 | Plumber Labour: Plumber | 0.04 | no | 700 | per day | 700 | 28 | |
| 4 | Skilled labour Skilled labour | 0.09 | no | 600 | per day | 600 | 54 | |
| 5 | Ordinary labour Ordinary labour | 0.07 | no | 550 | per day | 550 | 38.5 | |
| Sub-Total | 332.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 33.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 11.64 | |||||
| Total | 377.39 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 30.6 | ||||
| Grand Total | 407.99 | |||||||
| Rate per each | 408 | |||||||
| Rate per each | 408 | |||||||