Breakup

50 mm PP-R Union

Considering 1no. Of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 2" PP-R union 2" PP-R Union 1 no 732 each 732 732
2 Teflon Fittings fixing materials: Teflon Tape 2 pcs 17 per pcs 17 34
3 Plumber Labour: Plumber 0.07 no 700 per day 700 49
4 Skilled labour Skilled labour 0.12 no 600 per day 600 72
5 Ordinary labour Ordinary labour 0.15 no 550 per day 550 82.5
Sub-Total 969.5
Contractor's Profit 10% 0.1 96.95
Contractor's Overhead Expenses 3.5% 0.035 33.93
Total 1100.38
Add VAT with adjustment factor. 1.08108 7.5% 0.075 89.22
Grand Total 1189.6
Rate per each 1190
Rate per each 1190