Considering 1no. Of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 1" PP-R Gate-valve 1" PP-R Gate-Valve | 1 | no | 350 | each | 350 | 350 | |
| 2 | Teflon Fittings fixing materials: Teflon Tape | 2 | pcs | 17 | per pcs | 17 | 34 | |
| 3 | Plumber Labour: Plumber | 0.03 | no | 700 | per day | 700 | 21 | |
| 4 | Skilled labour Skilled labour | 0.08 | no | 600 | per day | 600 | 48 | |
| 5 | Ordinary labour Ordinary labour | 0.06 | no | 550 | per day | 550 | 33 | |
| Sub-Total | 486 | |||||||
| Contractor's Profit | 10% | 0.1 | 48.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 17.01 | |||||
| Total | 551.61 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 44.73 | ||||
| Grand Total | 596.34 | |||||||
| Rate per each | 596 | |||||||
| Rate per each | 596 | |||||||