Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 32 mm dia union 32 mm dia G.I. Union | 1 | no | 115 | each | 115 | 115 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 1.3 | pcs | 17 | per pcs | 17 | 22.1 | |
| 3 | Plumber Labour: Plumber | 0.05 | no | 700 | per day | 700 | 35 | |
| 4 | Skilled labour Skilled labour | 0.1 | no | 600 | per day | 600 | 60 | |
| 5 | Ordinary labour Ordinary labour | 0.1 | no | 550 | per day | 550 | 55 | |
| Sub-Total | 287.1 | |||||||
| Contractor's Profit | 10% | 0.1 | 28.71 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.05 | |||||
| Total | 325.86 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 26.42 | ||||
| Grand Total | 352.28 | |||||||
| Rate per each | 352 | |||||||
| Rate per each | 352 | |||||||