Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia union 50 mm dia G.I. Union | 1 | no | 190 | each | 190 | 190 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 2.05 | pcs | 17 | per pcs | 17 | 34.85 | |
| 3 | Plumber Labour: Plumber | 0.07 | no | 700 | per day | 700 | 49 | |
| 4 | Skilled labour Skilled labour | 0.12 | no | 600 | per day | 600 | 72 | |
| 5 | Ordinary labour Ordinary labour | 0.15 | no | 550 | per day | 550 | 82.5 | |
| Sub-Total | 428.35 | |||||||
| Contractor's Profit | 10% | 0.1 | 42.84 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 14.99 | |||||
| Total | 486.18 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 39.42 | ||||
| Grand Total | 525.6 | |||||||
| Rate per each | 526 | |||||||
| Rate per each | 526 | |||||||