Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 75 mm dia union 75 mm dia G.I. Union | 1 | no | 605 | each | 605 | 605 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 3.13 | pcs | 17 | per pcs | 17 | 53.21 | |
| 3 | Plumber Labour: Plumber | 0.1 | no | 700 | per day | 700 | 70 | |
| 4 | Skilled labour Skilled labour | 0.175 | no | 600 | per day | 600 | 105 | |
| 5 | Ordinary labour Ordinary labour | 0.2 | no | 550 | per day | 550 | 110 | |
| Sub-Total | 943.21 | |||||||
| Contractor's Profit | 10% | 0.1 | 94.32 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33.01 | |||||
| Total | 1070.54 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 86.8 | ||||
| Grand Total | 1157.34 | |||||||
| Rate per each | 1157 | |||||||
| Rate per each | 1157 | |||||||