Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 mm dia gate-valve 12 mm dia Gate Valve | 1 | no | 275 | each | 275 | 275 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 0.53 | pcs | 17 | per pcs | 17 | 9.01 | |
| 3 | Plumber Labour: Plumber | 0.025 | no | 700 | per day | 700 | 17.5 | |
| 4 | Skilled labour Skilled labour | 0.075 | no | 600 | per day | 600 | 45 | |
| 5 | Ordinary labour Ordinary labour | 0.05 | no | 550 | per day | 550 | 27.5 | |
| Sub-Total | 374.01 | |||||||
| Contractor's Profit | 10% | 0.1 | 37.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 13.09 | |||||
| Total | 424.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 34.42 | ||||
| Grand Total | 458.92 | |||||||
| Rate per each | 459 | |||||||
| Rate per each | 459 | |||||||